S-34.1 - Act respecting natural gas storage and natural gas and oil pipelines

Full text
275. The holder of a mining right granted under the Mining Act whose well or reservoir is not permanently closed by 20 September 2018 must, within 90 days after that date, submit a permanent well or reservoir closure and site restoration plan to the Minister as well as the guarantee required under Chapter IV.
2016, c. 35, s. 23.
Not in force
275. The holder of a mining right granted under the Mining Act whose well or reservoir is not permanently closed by (insert the date of coming into force of this section) must, within 90 days after that date, submit a permanent well or reservoir closure and site restoration plan to the Minister as well as the guarantee required under Chapter IV.
2016, c. 35, s. 23.