S-34.1 - Act respecting natural gas storage and natural gas and oil pipelines

Full text
126. A pipeline construction or use authorization holder must, as soon as their construction work has been completed, restore the land affected by the work to its former condition.
The Government determines, by regulation, the other conditions for carrying out such restoration work.
2016, c. 35, s. 23.
Not in force
126. A pipeline construction or use authorization holder must, as soon as their construction work has been completed, restore the land affected by the work to its former condition.
The Government determines, by regulation, the other conditions for carrying out such restoration work.
2016, c. 35, s. 23.