2107. Where the price of the work or services is estimated at the time the contract is entered into, the contractor or the provider of the services shall justify any increase of the price.
The client is bound to pay such increase only to the extent that it results from work, services or expenses that the contractor or the provider of services could not have foreseen at the time the contract was entered into.
1991, c. 64, a. 2107; I.N. 2014-05-01.
2107. Where the price of the work or services is estimated at the time the contract is entered into, the contractor or the provider of the services shall give the reasons for any increase of the price.
The client is bound to pay such increase only to the extent that it results from work, services or expenses that the contractor or the provider of services could not foresee at the time the contract was entered into.
1991, c. 64, a. 2107.