49.0.2. The report documenting the dam safety review must include(1) the opinion of the engineer in charge on the dam’s condition;
(2) the opinion of the engineer in charge on the functionality and reliability of discharge facilities;
(3) the opinion of the engineer in charge on the discharge capacity of the dam with respect to its safety check flood;
(4) if, on the reservoir rim, there are other dams whose failure consequence category is equal to or greater than “moderate”, the opinion of the engineer in charge on the dam’s stability with regard to its safety check flood;
(5) if applicable, the recommendations of the engineer in charge as to the need for an intervention at the locations, on the reservoir rim, through which overflow could occur during a flood equal to the dam’s safety check flood;
(6) if applicable, the recommendations of the engineer in charge in respect of the remedial work that, considering in particular the elements listed in 49.0.1, must be carried out to ensure the dam’s safety and the engineer’s opinion on the time required to carry out the work;
(7) if applicable, the opinion of the engineer in charge on the temporary measures and work required to ensure the dam’s safety until the remedial work is carried out;
(8) the recommendations of the engineer in charge in respect of the class and dam failure consequence category that should apply to the dam, together with, as the case may be, the dam failure analysis, rough inundation maps or characterization of the area referred to in section 18.