21. The fee for an application under the Act or a regulation for modification of an approval, certificate or permit referred to in this Order is $351, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
M.O. 2008-05-07, s. 21; M.O. 2016, s. 22; M.O. 2019-08-28, s. 19.
21. The fee for an application under the Act or a regulation for modification of an approval, certificate or permit referred to in this Order is $347, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
M.O. 2008-05-07, s. 21; M.O. 2016, s. 22; M.O. 2019-08-28, s. 19.
21. The fee for an application under the Act or a regulation for modification of an approval, certificate or permit referred to in this Order is $340, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
M.O. 2008-05-07, s. 21; M.O. 2016, s. 22; M.O. 2019-08-28, s. 19.
21. The fee for an application under the Act or its regulations for modification of an authorization, approval, certificate, permit or permission referred to in this Order is $340, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
The fee also does not apply to an application for modification of a certificate of authorization issued under section 22 of the Act for any project that relates exclusively to
(a)  an agricultural activity, including fish-farming;
(b)  the alteration without increase in capacity of a solid waste elimination or storage site governed by the Regulation respecting solid waste (chapter Q-2, r. 13);
(c)  wildlife development to which the third paragraph of section 2 of the Regulation respecting environmental impact assessment and review (chapter Q-2, r. 23) applies;
(d)  work that must be carried out by a regional county municipality to restore normal water flow in a watercourse pursuant to section 105 of the Municipal Powers Act (chapter C-47.1); or
(e)  work or activities arising from a state of emergency declared by a local municipality in accordance with section 42 of the Civil Protection Act (chapter S-2.3).
M.O. 2008-05-07, s. 21; M.O. 2016, s. 22.
21. The fee for an application under the Act or its regulations for modification of an authorization, approval, certificate, permit or permission referred to in this Order is $333, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
The fee also does not apply to an application for modification of a certificate of authorization issued under section 22 of the Act for any project that relates exclusively to
(a)  an agricultural activity, including fish-farming;
(b)  the alteration without increase in capacity of a solid waste elimination or storage site governed by the Regulation respecting solid waste (chapter Q-2, r. 13);
(c)  wildlife development to which the third paragraph of section 2 of the Regulation respecting environmental impact assessment and review (chapter Q-2, r. 23) applies;
(d)  work that must be carried out by a regional county municipality to restore normal water flow in a watercourse pursuant to section 105 of the Municipal Powers Act (chapter C-47.1); or
(e)  work or activities arising from a state of emergency declared by a local municipality in accordance with section 42 of the Civil Protection Act (chapter S-2.3).
M.O. 2008-05-07, s. 21; M.O. 2016, s. 22.
21. The fee for an application under the Act or its regulations for modification of an authorization, approval, certificate, permit or permission referred to in this Order is $328, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
The fee also does not apply to an application for modification of a certificate of authorization issued under section 22 of the Act for any project that relates exclusively to
(a)  an agricultural activity, including fish-farming;
(b)  the alteration without increase in capacity of a solid waste elimination or storage site governed by the Regulation respecting solid waste (chapter Q-2, r. 13);
(c)  wildlife development to which the third paragraph of section 2 of the Regulation respecting environmental impact assessment and review (chapter Q-2, r. 23) applies;
(d)  work that must be carried out by a regional county municipality to restore normal water flow in a watercourse pursuant to section 105 of the Municipal Powers Act (chapter C-47.1); or
(e)  work or activities arising from a state of emergency declared by a local municipality in accordance with section 42 of the Civil Protection Act (chapter S-2.3).
M.O. 2008-05-07, s. 21; M.O. 2016, s. 22.
21. The fee for an application under the Act or its regulations for modification of an authorization, approval, certificate, permit or permission referred to in this Order is $285, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
The fee also does not apply to an application for modification of a certificate of authorization issued under section 22 of the Act for any project that relates exclusively to
(a)  an agricultural activity, including fish-farming;
(b)  the alteration without increase in capacity of a solid waste elimination or storage site governed by the Regulation respecting solid waste (chapter Q-2, r. 13);
(c)  wildlife development to which the third paragraph of section 2 of the Regulation respecting environmental impact assessment and review (chapter Q-2, r. 23) applies;
(d)  work that must be carried out by a regional county municipality to restore normal water flow in a watercourse pursuant to section 105 of the Municipal Powers Act (chapter C-47.1); or
(e)  work or activities arising from a state of emergency declared by a local municipality in accordance with section 42 of the Civil Protection Act (chapter S-2.3).
M.O. 2008-05-07, s. 21.
21. The fee for an application under the Act or its regulations for modification of an authorization, approval, certificate, permit or permission referred to in this Order is $281, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
The fee also does not apply to an application for modification of a certificate of authorization issued under section 22 of the Act for any project that relates exclusively to
(a)  an agricultural activity, including fish-farming;
(b)  the alteration without increase in capacity of a solid waste elimination or storage site governed by the Regulation respecting solid waste (chapter Q-2, r. 13);
(c)  wildlife development to which the third paragraph of section 2 of the Regulation respecting environmental impact assessment and review (chapter Q-2, r. 23) applies;
(d)  work that must be carried out by a regional county municipality to restore normal water flow in a watercourse pursuant to section 105 of the Municipal Powers Act (chapter C-47.1); or
(e)  work or activities arising from a state of emergency declared by a local municipality in accordance with section 42 of the Civil Protection Act (chapter S-2.3).
M.O. 2008-05-07, s. 21.
21. The fee for an application under the Act or its regulations for modification of an authorization, approval, certificate, permit or permission referred to in this Order is $276, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
The fee also does not apply to an application for modification of a certificate of authorization issued under section 22 of the Act for any project that relates exclusively to
(a)  an agricultural activity, including fish-farming;
(b)  the alteration without increase in capacity of a solid waste elimination or storage site governed by the Regulation respecting solid waste (chapter Q-2, r. 13);
(c)  wildlife development to which the third paragraph of section 2 of the Regulation respecting environmental impact assessment and review (chapter Q-2, r. 23) applies;
(d)  work that must be carried out by a regional county municipality to restore normal water flow in a watercourse pursuant to section 105 of the Municipal Powers Act (chapter C-47.1); or
(e)  work or activities arising from a state of emergency declared by a local municipality in accordance with section 42 of the Civil Protection Act (chapter S-2.3).
M.O. 2008-05-07, s. 21.
21. The fee for an application under the Act or its regulations for modification of an authorization, approval, certificate, permit or permission referred to in this Order is $273, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
The fee also does not apply to an application for modification of a certificate of authorization issued under section 22 of the Act for any project that relates exclusively to
(a)  an agricultural activity, including fish-farming;
(b)  the alteration without increase in capacity of a solid waste elimination or storage site governed by the Regulation respecting solid waste (chapter Q-2, r. 13);
(c)  wildlife development to which the third paragraph of section 2 of the Regulation respecting environmental impact assessment and review (chapter Q-2, r. 23) applies;
(d)  work that must be carried out by a regional county municipality to restore normal water flow in a watercourse pursuant to section 105 of the Municipal Powers Act (chapter C-47.1); or
(e)  work or activities arising from a state of emergency declared by a local municipality in accordance with section 42 of the Civil Protection Act (chapter S-2.3).
M.O. 2008-05-07, s. 21.
21. The fee for an application under the Act or its regulations for modification of an authorization, approval, certificate, permit or permission referred to in this Order is $268, unless a provision of the Order sets a different fee for the application.
The fee set out in the first paragraph does not apply to an application for only 1 change or modification to the information or documents already provided in support of an application.
The fee also does not apply to an application for modification of a certificate of authorization issued under section 22 of the Act for any project that relates exclusively to
(a)  an agricultural activity, including fish-farming;
(b)  the alteration without increase in capacity of a solid waste elimination or storage site governed by the Regulation respecting solid waste (chapter Q-2, r. 13);
(c)  wildlife development to which the third paragraph of section 2 of the Regulation respecting environmental impact assessment and review (chapter Q-2, r. 23) applies;
(d)  work that must be carried out by a regional county municipality to restore normal water flow in a watercourse pursuant to section 105 of the Municipal Powers Act (chapter C-47.1); or
(e)  work or activities arising from a state of emergency declared by a local municipality in accordance with section 42 of the Civil Protection Act (chapter S-2.3).
M.O. 2008-05-07, s. 21.