12. The fees payable by an applicant for an authorization issued under section 31.5, 160 or 196 of the Act for a project covered by more than one rate class in Schedule I, II or III are,
(1)  for applications under section 31.5, the fees set out in section 10 for the highest rate class that applies to the project; and
(2)  for applications under section 160 or 196, the fees set out in section 10.1 for the highest rate class that applies to the project.
The fees payable by an applicant for an authorization issued for a project that is partly exempted from the environmental impact assessment and review procedure under section 31.7.2 of the Act and that is covered by more than one rate class in Schedule I are, for each of the steps in the procedure that remain applicable, the fees set out in section 10 for the highest rate class that applies to the project.
M.O. 2008-05-07, s. 12; M.O. 2016, s. 13; M.O. 2018-03-13, s. 3.
12. The fees payable by an applicant for a certificate of authorization issued under section 31.5, 160 or 196 of the Act for a project covered by more than one rate class in Schedule I, II or III are,
(1)  for applications under section 31.5, the fees set out in section 10 for the highest rate class that applies to the project; and
(2)  for applications under section 160 or 196, the fees set out in section 10.1 for the highest rate class that applies to the project.
The fees payable by an applicant for a certificate of authorization issued for a project that is partly exempted from the environmental impact assessment and review procedure under section 31.6 of the Act and that is covered by more than one rate class in Schedule I are, for each of the steps in the procedure that remain applicable, the fees set out in section 10 for the highest rate class that applies to the project.
M.O. 2008-05-07, s. 12; M.O. 2016, s. 13.
12. The fees for an application for authorization under section 31.5 or 31.6 of the Act for a project covered by more than one class or subclass of projects referred to in Schedule I are the fees set out in section 10 for the highest rate class applicable to the project.
M.O. 2008-05-07, s. 12.