32. To obtain the Board’s approval, a pressure installation declaration must be sent to the Board by the installer at least 30 days before the completion of the work on the form provided for that purpose. The declaration must include(1) the address of the worksite;
(2) the name, address and telephone number of the person for whom the work is performed;
(3) the name, address, telephone number, permit number and licence number of the person performing the work;
(4) if applicable, the name of the engineer who designed or supervised the installation;
(5) the dates on which the installation begins and ends;
(6) the use of the building and the use of the installation;
(7) the nature of the work performed;
(8) the characteristics of the boiler or vessel, in particular its registration number, serial number, power, manufacturer’s name and, in the case of a refrigeration pressure installation, the serial number, power and compressor manufacturer’s name;
(9) the fluid used; and
(10) the pressure setting and the relieving capacity of the safety device.