A-19.1 - Act respecting land use planning and development

Full text
165.4.2. Within 30 days after receipt of the application for the building permit or certificate, the competent municipal officer shall inform the applicant of the admissibility or inadmissibility of the application under the applicable municipal regulations, and issue the permit or certificate if the application is admissible.
However, sections 165.4.3 to 165.4.17 apply prior to the issue of the permit or certificate
(1)  if the application concerns a new hog farm in the territory of the municipality;
(2)  if the application involves an increase of more than 3,200 kilograms in the annual production of phosphoric anhydride by an existing hog farm, either by itself or in combination with the production resulting from an application made less than five years before.
For the purposes of the second paragraph, a hog farm is deemed to be a new hog farm if it cannot be operated in the immovable where the existing hog farm is operated or in an immovable contiguous to it or that would be contiguous if it were not separated by a watercourse, a thoroughfare or a public utility network.
2004, c. 20, s. 10.