17. The holder of the revoked licence may begin the work provided for by the permanent well closure and site restoration plan once the following conditions are met:
(1)  the holder has received the notice of permanent well closure notified by the Minister;
(2)  the holder has informed in writing the owner or lessee, the local municipality and the regional county municipality, as applicable, at least 30 days before the work begins if the site concerned is located in whole or in part on private land or land leased by the State or in the territory of a local municipality; and
(3)  the holder has informed the Minister in writing, at least seven days before the work begins, of the work start date.
2022, c. 10, s. 1.
In force: 2022-08-23
17. The holder of the revoked licence may begin the work provided for by the permanent well closure and site restoration plan once the following conditions are met:
(1)  the holder has received the notice of permanent well closure notified by the Minister;
(2)  the holder has informed in writing the owner or lessee, the local municipality and the regional county municipality, as applicable, at least 30 days before the work begins if the site concerned is located in whole or in part on private land or land leased by the State or in the territory of a local municipality; and
(3)  the holder has informed the Minister in writing, at least seven days before the work begins, of the work start date.
2022, c. 10, s. 1.