47. Installation conditions: Construction of a privy is permitted provided the following conditions are met:a) the soil must be high permeability or permeable soil;
b) the underground water, bedrock or any layer of impermeable or low permeability soil must be at least 1.2 m below the surface;
c) the grade of the site must be less than 30%.