C-65.1, r. 8.01 - Pilot project to facilitate payment to enterprises that are parties to public construction work contracts and related public subcontracts

Français
Texte complet
38. Payment by one of the parties to the contract pursuant to the adjudicator’s decision is made under protest, namely without prejudice and subject to the payor’s right to reimbursement of all or a portion of the amount of money as a consequence of a subsequent award by an arbitrator or a decision by a court of general jurisdiction.
A.M. 2018-01, s. 38.
In force: 2018-08-02
38. Payment by one of the parties to the contract pursuant to the adjudicator’s decision is made under protest, namely without prejudice and subject to the payor’s right to reimbursement of all or a portion of the amount of money as a consequence of a subsequent award by an arbitrator or a decision by a court of general jurisdiction.
A.M. 2018-01, s. 38.