55. A public body must record in a report the evaluation of any contractor whose performance is considered to be unsatisfactory.
The situation of a contractor whose rank has been modified by a public body or from whom a public body no longer solicits task order contracts is not to be considered unsatisfactory performance pursuant to the second paragraph of section 20.1.
O.C. 532-2008, s. 55; D. 142-2025, s. 39.