41.2. The public body also publishes in the electronic tendering system, within 90 days of the end of a contract referred to in section 41, the final description of the contract. The period is extended to 120 days for a contract entered into following a joint call for tenders referred to in section 15 of the Act.
The final description of the contract contains at least
1°  the name of the contractor, the date of the end of the contract and the total amount paid;
2°  in the case of a task order contract involving several contractors, their respective name and the total amount paid to each of them;
3°  in the case of a contract that involves options, the type and number of options exercised and the total amount paid following their exercise; and
4°  the amount of any additional expenditure that has not been published in accordance with section 41.1.
O.C. 431-2013, s. 14; D. 142-2025, s. 35.
41.2. The public body also publishes in the electronic tendering system, within 90 days of the end of a contract referred to in section 41, the final description of the contract. The period is extended to 120 days for a contract entered into following a joint call for tenders referred to in section 15 of the Act.
The final description of the contract contains at least
1°  the name of the contractor, the date of the end of the contract and the total amount paid;
2°  in the case of a task order contract involving several contractors, their respective name and the total amount paid to each of them; and
3°  in the case of a contract that involves options, the type and number of options exercised and the total amount paid following their exercise.
O.C. 431-2013, s. 14.