18.8. Having taken cognizance of the comments, if any, the public body decides whether it upholds the conclusions of its report or not.
If the public body upholds the conclusions of its report, it rejects the tender not later than before the expiry of the period of validity of tenders.
O.C. 431-2013, s. 5; D. 142-2025, s. 14.
18.8. Having taken cognizance of the comments, if any, the committee decides whether it upholds the conclusions of its report or not.
If the committee does not uphold the conclusions of its report, the contract rules compliance monitor sends a copy of the updated report to the chief executive officer of the public body.
If the committee upholds the conclusions of its report, the contract rules compliance monitor sends a copy of the updated report, if applicable, to the chief executive officer of the public body, who authorizes the rejection of the tender not later than before the expiry of the period of validity of tenders.
O.C. 431-2013, s. 5.