The plans and specifications must contain information on the following:1° towers;
2° upper and lower stations;
3° sheaves and sheave assemblies;
4° counterweight sheaves;
5° deropement equipment and switches;
6° main drive;
7° rope grips;
8° hangers and spring boxes;
9° hangers and chairs, or cars, or cabins;
10° brakes and backstops;
11° tensioning systems and details;
12° foundations of all structures;
13° electric power and lightning protection;
14° electric controls and safety schematics;
15° communication systems;
16° hydraulic schematic systems;
17° haul and counterweight rope details;
18° structures or buildings;
19° evacuation equipment (seats, ropes);
20° service and inspection platforms;
21° ramps; and
22° elevation plan.