B-1.1, r. 2 - Construction Code

Français
Texte complet
4.15. Following the carrying out of the construction work referred to in section 4.01, other than maintenance, repair or demolition work, the contractor or owner-builder shall
1°  submit the elevator or the elevating device to the tests and inspections referred to in section 8.10 of the Code or Annex A of the standard, as the case may be; and
2°  send to the Board, not later than 20 days after the date of completion of the work or the re-use of the elevator or elevating device, a declaration of work including the following information:
a)  the components that were subject to the tests and inspections referred to in paragraph 1;
b)  the date on which the tests and inspections were conducted together with the name and title of the person by whom they were performed;
c)  the name, address, telephone number and email address of the owner;
d)  the address of the work site and the nature of the work;
e)  the type, trademark, model, technical features and the name of the manufacturer of the elevator or the elevating device.
D. 848-2024, s. 1.