C-65.1 - Act respecting contracting by public bodies

Full text
21.35. (Repealed).
2012, c. 25, s. 10; 2017, c. 27, s. 124; 2022, c. 18, s. 30.
21.35. The Authority may require that an enterprise communicate any information needed for the purposes of this chapter. The enterprise must communicate the information to the Authority within the time limit specified by the Authority. If the enterprise fails to do so, the Authority may, as applicable, cancel the application for authorization or suspend the authorization.
The Authority may also cancel the application for authorization or suspend the authorization of an enterprise that fails to communicate to the Associate Commissioner referred to in section 21.30, within the time the Commissioner specifies, the information needed for the purposes of this chapter that the Commissioner requests.
An enterprise whose application for authorization is cancelled under this section may not file a new application with the Authority within 12 months after the cancellation unless the Authority allows it.
An enterprise whose authorization is suspended may nonetheless perform a public contract or subcontract if the enterprise was authorized on the date the contract or subcontract was entered into or, in the case of an enterprise responding to a call for tenders, if it was authorized on the closing date and time for the receipt and opening of tenders.
2012, c. 25, s. 10; 2017, c. 27, s. 124.
21.35. The Authority may require that an enterprise communicate any information needed for the purposes of this chapter. The enterprise must communicate the information to the Authority within the time limit specified by the Authority. If the enterprise fails to do so, the Authority may revoke its authorization.
2012, c. 25, s. 10.