46.0.17. At least 15 days before undertaking work relating to flood protection works or accessing the works, the municipality must notify, in writing, any land owners concerned by the work to be carried out and inform them of the rights the municipality has with respect to the flood protection works. The municipality must also inform the land owners of the nature and expected duration of the work, where applicable.
Despite the first paragraph, the municipality may undertake work relating to flood protection works without first notifying the land owners concerned by the work to be carried out in urgent circumstances or in order to prevent serious or irreparable harm or damage to human beings, ecosystems, other living species, the environment or property.
2021, c. 7, s. 91.