A-2.001 - Act respecting the acceleration of certain infrastructure projects

Full text
60. Within 15 days after receiving the project notice, the local municipality issues to the public body the authorizations necessary to carry out the project or sends the public body a notice indicating that the project is not in conformity with the planning by-laws applicable in the territory. The notice must specify which by-laws impede the issuance of those authorizations.
2020, c. 27, s. 60.