23. An owner may, in respect of a high-capacity dam, submit a safety program to the Minister for approval that, if approved, will replace the regulatory standards prescribed pursuant to this Act and indicated in the program, other than the safety standards referred to in section 15.
The Minister shall approve the program submitted by the owner, with or without conditions, if the owner shows that the resulting level of safety under the program is equal to or greater than the level of safety that would be achieved through compliance with the regulatory standards. The Minister may also approve any safety program modification submitted by the owner that meets the requirements of this section.
No safety program may be established for a period exceeding five years.
2000, c. 9, s. 23; 2022, c. 8, s. 152.
23. An owner may, in respect of a high-capacity dam, submit a safety program to the Minister for approval that, if approved, will replace the regulatory standards prescribed pursuant to this Act and indicated in the program, other than the safety standards referred to in section 15.
The Minister shall approve the program submitted by the owner, with or without conditions, if the owner shows that the resulting level of safety under the program is equal to or greater than the level of safety that would be achieved through compliance with the regulatory standards. The Minister may also approve any safety program modification submitted by the owner that meets the requirements of this section.
A decision by the Minister refusing approval of a safety program or safety program modification may be contested by the owner of the works before the Administrative Tribunal of Québec within 30 days of notification.
No safety program may be established for a period exceeding five years.
2000, c. 9, s. 23.