R-25.02 - Act respecting the Réseau électrique métropolitain

Full text
19. Failing agreement between the local municipality and the Fund, the Fund may, on the expiry of 60 days following the date on which the municipality received the notice required under the first paragraph of section 16, start occupying the roads and, if applicable, commence the work specified in the notice in accordance with the plans and specifications sent to the municipality without having to pay the municipality an amount of money or any other consideration.
The Fund and a local municipality may agree on a different time limit than the one set out in the first paragraph for negotiation purposes. Such an agreement to extend the deadline may also, under section 15, be entered into between the Fund and the urban agglomeration of Montréal.
2017, c. 17, s. 19.