C-7.01 - Act respecting the Centre d’acquisitions gouvernementales

Full text
8. The Centre must establish a plan for government procurement under its responsibility that takes into account the needs of public bodies.
The government procurement plan must be sent to the Conseil du trésor.
The Chair of the Conseil du trésor determines the information the plan must include, the period it covers, the time limit for sending it to the Conseil du trésor, its form, and the schedule for any revisions of it.
2020, c. 2, s. 1.
Not in force
8. The Centre must establish a plan for government procurement under its responsibility that takes into account the needs of public bodies.
The government procurement plan must be sent to the Conseil du trésor.
The Chair of the Conseil du trésor determines the information the plan must include, the period it covers, the time limit for sending it to the Conseil du trésor, its form, and the schedule for any revisions of it.
2020, c. 2, s. 1.