21.18. An enterprise that responds to a call for tenders for a public contract or subcontract must hold an authorization on the date it submits its bid. An enterprise that enters into a public contract or subcontract by mutual agreement must hold an authorization on the date the contract or subcontract is entered into.
An authorization must be maintained throughout the contract or subcontract.
2012, c. 25, s. 10; 2022, c. 18, s. 21.
21.18. An enterprise that enters into a contract with a public body or that enters into a public subcontract must hold an authorization on the date the contract or subcontract is entered into. In the case of a consortium, every enterprise in the consortium must hold an authorization on that date.
Moreover, an enterprise that responds to a call for tenders for a public contract or subcontract must hold an authorization on the date it submits its bid, unless the call for tenders specifies a different date which precedes the date the contract is entered into.
An authorization must be maintained throughout the contract or subcontract.
2012, c. 25, s. 10.